SceneryCarHouse fade

Hot Topics

Service Request Online

Do you have a Council related problem that requires attention?

Proposed Project Martha

Planners reports from HDC and WRC for consideration at the hearing are now available.

Proposed Wind Farm

Submissions have now closed

Swimming Season

Ngatea and Waihi pools now closed, Paeroa closes 7 April.

It's more than just a job

View our latest job vacancies and apply online.

Kerbside Collections

Week 2 begins Monday 18 March 2019

25 February 2019

Kerepehi Water Treatment Plant

Two new drinking water reservoirs

The Council is installing two new 4,015m3 drinking water reservoirs at the Kerepehi Water Treatment Plant. The existing reservoir holds 2000m3, which is not enough to keep Hauraki Plains taps running for long in the event of an unexpected plant shutdown. 

The addition of the new tanks will allow the storage 10,000m3 of clean drinking water, which means about 24 hours of supply in the event of a temporary plant shutdown. 

Site testing

The site was pre-loaded with gravel due to the unstable ground conditions of the Plains. The weight of this gravel compresses the site to find out what will happen to the ground when the weight of a structure is added. The gravel was then removed.

The testing revealed a few things that required a redesign to the reservoir foundations. Not so surprising given the nature of building on the Plains but this held up work at the site for a couple of weeks. It also resulted in a slight increase to our overall investment in the project.


18 March 2019

Reservoirs nearing completion

Both reservoirs are now nearing completion with the roof on the easterly tank finished and nearly completed on the second tank. Work will then continue on the inside of the reservoirs.

Council's Construction and Maintenance team will install the remainder of the pipe work between the two tanks.

The connection to the water treatment plant will require two water shutdowns. These will be notified to those affected nearer to the date.

Projects water road

Road resurfacing

Kerepehi Town Road 

Surface work to Kerepehi Town Road will be completed in April.

A large trench had been dug across the road while new water pipes were installed.

Water shutdowns

Dates to be advised.

We appreciate your patience and understanding while we work to complete this project.

 

Kerephei water reservoirs

Expected completion

The new reservoirs are on track to be up and running in April 2019.